The example is shown although there are some from which a construction process differs. After carrying out precedent boring by Auger and injecting slurry for to stabilize the pile circumference, the pile having a special tip shoe and tip metallic is inserted into the bored hole, a top or a tip part is driven by free drop hammer, and bearing capacity is made to ensure.
It can construct in a comparatively low vibration and noise, and evaluation of the bearing capacity calculation formula is higher than a pre-boring with root hardening cement slurry method of construction.
For application of pile diameter, about 300-600mm and the maximum pile length are about 40m.